A flat was promised for a particular date, and that date has passed. Under Section 18 of the Real Estate (Regulation and Development) Act, 2016 (RERA), the buyer, called the allottee, has a choice. The allottee may withdraw from the project and demand a refund of everything paid, with interest and compensation. Or the allottee may stay in the project and claim interest for every month of delay until possession is handed over. In Maharashtra, the interest rate is fixed by rule at the State Bank of India’s highest marginal cost of lending rate (MCLR) plus two per cent. This article explains when Section 18 applies, how each option works, how the interest is worked out and who decides what.

When Section 18 applies

Section 18(1) applies where the promoter fails to complete, or is unable to give possession of, an apartment, plot or building:

The trigger is therefore the agreed date of possession in the agreement for sale. Section 18 also has two further limbs. Section 18(2) makes the promoter liable to compensate the allottee for loss caused by a defective title to the land. Section 18(3) makes the promoter liable to pay compensation for failure to discharge any other obligation under RERA, the rules, the regulations or the agreement. This article concerns Section 18(1).

The two options

Option 1: Withdraw and take a refund

If the allottee wishes to withdraw from the project, the promoter is liable, on demand, to return the amount received in respect of the apartment, with interest at the prescribed rate, including compensation in the manner provided under the Act. The refund is without prejudice to any other remedy available to the allottee.

Option 2: Stay and claim interest for the delay

Under the proviso to Section 18(1), where the allottee does not intend to withdraw, the promoter must pay interest for every month of delay, till the handing over of possession, at the prescribed rate. The Supreme Court described the proviso in these terms in Imperia Structures Ltd v. Anil Patni (2020) 10 SCC 783: the allottee “is entitled to and must be paid interest for every month of delay till the handing over of the possession”.

Withdraw (refund) Stay (delay interest)
What you get All amounts paid, with interest Monthly interest until possession
What happens to the flat Allotment ends You keep the flat
Rate in Maharashtra SBI highest MCLR + 2% SBI highest MCLR + 2%
Compensation Can be claimed before the Adjudicating Officer Can be claimed for other losses, subject to the facts
Who decides the refund or interest MahaRERA MahaRERA

What the Supreme Court said in Newtech Promoters

The leading case is Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh (Supreme Court, 11 November 2021, LL 2021 SC 641), decided by a bench of Justices U.U. Lalit, Ajay Rastogi and Aniruddha Bose. Three points matter to buyers.

The right to a refund is unconditional. The Court held that where the promoter fails to give possession within the time stipulated in the agreement, the allottee’s right to demand a refund is not dependent on contingencies or stipulations in the agreement. The promoter is under an obligation to refund, with interest at the rate prescribed by the State Government, if the allottee wishes to withdraw. The Court treated this as a right the promoter cannot defeat by pleading reasons for the delay.

Refund and interest belong to the Authority. The Regulatory Authority (in Maharashtra, MahaRERA) has the power to direct refund of the amount, interest on the refund, and interest for delayed delivery of possession. These are largely matters of arithmetic once the payments and dates are established.

Compensation belongs to the Adjudicating Officer. The determination of compensation, and interest on it, under Sections 12, 14, 18 and 19 is reserved for the Adjudicating Officer under Section 71, read with Section 72. The Court said that extending the Adjudicating Officer’s remit to refund claims “would be against the mandate of the Act 2016”.

The interest rate in Maharashtra

RERA leaves the rate of interest to be prescribed by State rules. Rule 18 of the Maharashtra Real Estate (Regulation and Development) (Registration of real estate projects, Registration of real estate agents, rates of interest and disclosures on website) Rules, 2017 provides that the rate payable by the promoter to the allottee, or by the allottee to the promoter, “shall be the State Bank of India highest Marginal Cost of Lending Rate plus two percent”. A proviso says that if the SBI MCLR is not in use, it will be replaced by such benchmark lending rate as SBI may fix for lending to the general public.

Two points follow. First, the same rate applies both ways: a buyer who pays late owes interest at the same rate. Second, the rate changes over time as SBI revises its MCLR. Check SBI’s published rate when you compute a claim, and check which date’s rate an order applies.

Rule 19 of the same Rules requires the promoter to make any refund, with applicable interest and compensation, within thirty days from the date on which it becomes due and payable, and to report every such instance to the Authority within thirty days.

How to compute the claim: a worked example

Suppose (hypothetically) a buyer agreed to buy a flat for Rs 1,00,00,000 under an agreement for sale that promised possession by 31 December 2023. The buyer paid Rs 20,00,000 on 1 April 2021 and Rs 30,00,000 on 1 April 2022, a total of Rs 50,00,000. Suppose also that SBI’s highest MCLR is 9 per cent, so the Rule 18 rate is 11 per cent a year. The example assumes simple interest.

If the buyer withdraws and the order is dated 31 December 2026

Interest on a refund is usually computed from the date each payment was made:

Payment Date paid Period to 31 Dec 2026 Interest at 11%
Rs 20,00,000 1 Apr 2021 about 5.75 years about Rs 12,65,000
Rs 30,00,000 1 Apr 2022 about 4.75 years about Rs 15,67,500
Total about Rs 28,32,500

The refund claim would be roughly Rs 50,00,000 plus Rs 28,32,500, before any compensation the Adjudicating Officer may award. Interest typically continues until actual payment.

If the buyer stays and possession is given on 31 December 2026

Delay interest runs from the agreed possession date, 1 January 2024, to the date of possession: 36 months. At 11 per cent a year on Rs 50,00,000, that is about Rs 5,50,000 a year, or about Rs 16,50,000 for the three years. Because the base is the amount actually paid, a buyer who pays further instalments during the delay period will see the base increase.

The two figures differ because they measure different things. A refund puts the buyer back where they started, with interest for the use of their money from the day it was paid. Delay interest compensates only for the period after the promised date.

Compensation before the Adjudicating Officer

Compensation is a separate claim. Under Section 71, the Authority appoints an Adjudicating Officer to adjudge compensation under Sections 12, 14, 18 and 19. Under Section 72, the officer must have regard to factors such as the amount of disproportionate gain or unfair advantage made by the promoter, the amount of loss caused to the allottee, the repetitive nature of the default and other relevant factors.

In Maharashtra, Rule 7 of the Maharashtra Real Estate (Regulation and Development) (Recovery of Interest, Penalty, Compensation, Fine payable, Forms of Complaints and Appeal, etc.) Rules, 2017 provides for a complaint to the Adjudicating Officer in Form B, filed through the office of the Authority with a fee of Rs 5,000. Compensation, unlike interest, must be proved: keep evidence of rent paid, loan interest, and other losses actually suffered.

Choosing between the two

There is no right answer for everyone. Considerations that usually matter include:

Other forums and enforcement

RERA is not the only route. In Imperia Structures v. Anil Patni (2020), the Supreme Court held that remedies under the Consumer Protection Act remain available alongside RERA. Buyers should not, however, pursue the same claim in two forums at once.

Getting an order is only half the battle. Under Section 40(1) of RERA and Rule 3 of the recovery Rules, interest, penalty and compensation are recoverable as arrears of land revenue. MahaRERA Circular No. 51/2025 dated 18 November 2025 sets out a procedure for enforcing such orders: a non-compliance application after 60 days, disclosure of the promoter’s assets on affidavit, a revenue recovery certificate to the Collector to attach and sell the promoter’s assets, and, where needed, reference to the civil court under Order XXI Rule 41 of the Code of Civil Procedure.

Frequently Asked Questions

Can the builder refuse a refund by citing reasons for the delay?

The Supreme Court held in Newtech Promoters v. State of UP (2021) that the allottee’s right to a refund on the promoter’s failure to give possession by the agreed date does not depend on contingencies or stipulations in the agreement. The promoter’s explanations for delay are generally not a defence to a refund under Section 18(1).

What interest rate applies in Maharashtra?

Rule 18 of the Maharashtra RERA Rules, 2017 fixes it at the State Bank of India’s highest MCLR plus two per cent. The same rate applies when an allottee pays the promoter late.

Who decides compensation, MahaRERA or the Adjudicating Officer?

MahaRERA decides refund and interest. Compensation is decided by the Adjudicating Officer under Section 71, applying the factors in Section 72, on a complaint in Form B.

Is there a time limit for claiming delay interest?

RERA does not prescribe a limitation period for complaints. In September 2026, the Allahabad High Court (Antriksh Developers and Promoters Pvt. Ltd. v. Shyam Sundar Agarwal) held that an allottee who stays in a project can claim delay interest for each month of delay and that Section 18(1) sets no limitation for that claim, while in October 2026 the Tamil Nadu Real Estate Appellate Tribunal applied the Limitation Act’s three-year period to compensation claims. Filing promptly is the safer course.

If I take possession, do I lose my claim to delay interest?

Delay interest under the proviso to Section 18(1) runs until possession is handed over, so taking possession stops further accrual but does not, by itself, cancel interest already accrued. Read any possession letter or undertaking carefully before signing it.

This article is for general information and is not legal advice.

Asahi Legal regularly acts in matters of this kind before the Bombay High Court, NCLT/NCLAT and other forums. For a personal consultation, you may book an appointment.

This article is for general information only and is not legal advice or an invitation to engage the firm. Laws and judgments change; please obtain specific legal advice before acting.

Chat on WhatsApp